Project Information
Duration
3 months
Client
Dept of Air Force & ACC
Budget
Under budget
Location
Nellis Air Force Base, NV
More Details of Project
- Lira Electric repaired the active vehicle barriers and installed the corresponding gear, panels, and transformer.
- Collaborated with power generation distributors including Cummins and Graybar to receive and install the job’s gear and transformer.
- Worked together with Northcon and the Department of the Air Force Air Combat Command to meet high expectations and very detailed specifications.
- 10 Lira Electric Professionals made up the implementation team
Project took 3 months and was completed on time and under budget